Bundelkhand Expressway

 
S. No. Subject Uploaded Date View/Download
  Bundelkhand Expressway Project Map Size: 192KB | Lang: English 21/01/2020 Click here to View/Download

Bundelkhand Expressway Access Controlled Project (Green Field)

For Omni-directional development in the Bundelkhand area, especially in less developed districts like Chitrakoot, Banda, Hamirpur, and Jalaun the State Government has pledged to construct Bundelkhand Expressway. This expressway will link the Bundelkhand area from national capital Delhi through Agra-Lucknow expressway and Yamuna expressway as well as will play a vital role in the development of Bundelkhand area.

  • Starting point of the project:- Near Bharatkoop at Jhansi-Allahabad National Highway Number-35 in district Chitrakoot.
  • Ending point of the project:- Near village Kudrail in district Etawah on Agra-Lucknow expressway.
  • Length of the project:- Total 296.070 KM.
  • Districts benefited from the project: Chitrakoot, Banda, Mahoba, Hamirpur, Jalaun, Auraiya and Etawah.
  • Progress of construction of Bundelkhand expressway til 31 May 2020 is 05%

Form of Expressway:-

This expressway will be of 04 lanes (Expandable up to 06 lanes) with 06 lane wider structures. Width of ROW (Right Of Way) of the project is 110 Meter; a service road of 3.75 M width will be constructed at one side of the express way in staggered form so that residents of nearby villages of the project area may get smooth transportation facility.

Main rivers falling on alignment:- Bagen, Ken, Shyama, Chandawal, Birma, Yamuna, Betwa and Sengar.

Proposed structures on expressway:- Total 04 Rail Over Bridges, 14 Large bridges, 06 Toll Plazas, 07 Ramp Plaza, 266 small bridges and 18 Fly Overs will also be constructed on expressway.

Details of packages and developers of project:-

This project has been divided into 06 packages wherein contracts have been constituted with developers for construction work after e-tendering as under:-

Package No. Name of Package Length (In KM) Name of Developer Contracted Cost (IN crore Rs.)
1 Chainage (-)0+790 to Chainage 49+700 (Gonda, district Chitrakoot to Manokhar, upto district Banda) 50.490 M/s Apco Infratech Pvt. Ltd. 1268.60
2 Chainage 49+700 to 100+000 (Manokhar, district Banda to Kaouhri, up to district Mahoba) 50.300 M/s Apco Infratech Pvt. Ltd. 1245.63
3 Chainage 100+000 to Chainage 149+000 (Kaouhri, district Mahoba to Brolikharka, district Hamirpur) 49.000 M/s Ashoka Bildcon Ltd. 1079.52
4 Chainage 149+000 to Chainage 200+000 (Brolikharka, district Hamirpur to Salabaad, district Jalaun) 51.000 M/s Gavar Construction Limited 1396.00
5 Chainage 200+000 to Chainage 250+000 (Salabaad, district Jalaun to Bakhariya, district Auraiya) 50.00 M/s Gavar Construction Limited 1415.00
6 Chainage 250+000 to Chainage 295+280 (Bakhariya, district Auraiya to Kudrail, district Etawah) 45.280 M/s Dilip Bildcon Limited 1362.06
 

Total

296.070   7766.80

Benefits from Project:-

  • With the construction of expressway, Bundelkhand area will be linked with fast and smooth traffic corridor through Agra-Lucknow expressway and Yamuna expressway.
  • The way of Omni-directional development of Bundelkhand area will be strengthen. Important savings in consumption of fuel and control over pollution will also be possible being the expressway is access controlled.
  • Area covered under the project will be economically and socially developed as well as enhancement in the agriculture, commerce, tourism and industrial income will also be experienced.
  • To link the various manufacturing units, development centers and agricultural productive areas with the national capital, established in the areas covered under expressway, an industrial corridor will be developed which will assist in the Omni directional development of the area. 
  • Opportunities will also be available for establishment of Industrial Training Institutes, Teaching and Training Institutes and Medical Institutes etc. near expressway.
  • Expressway will act as catalyst for establishment of Handloom industry, food processing units, storages, market and Milk based industries.

Progress of land acquisition for construction of expressway:-

Approximately 95.01% land has been purchased/acquisition for the project. Till date a total of 3462.2787 hectare land has been purchased/acquisitioned by UPEIDA for the project.

For better development of Bundelkhand area and to generate new opportunities of employment, government has decided to construct Bundelkhand expressway. After competition of this project, the ambitious project Defense Industrial Corridor will get automatic boosts.

SALIENT FEATURES OF THE PROJECT

Starting Point Near Bharatkoop in District Chitrakoot.
End Point Near Kudrail village (before 16 KM) at NH-91 (Etawah Bewar Road)
Highlights
  • Estimated Total Length - 296.07 kms
  • ROW - 110 Meters
  • Carriageway - 4 lanes (expandable upto 6 lanes) but all will be constructed as per 6 lanes..
  • Provision of Service Road
  • Districts Covered - Chitrakoot, Banda, Hamirpur, Jalaun and Auraiya.
  • Total Access Controlled Expressway
  • Provision for Underpasses for Vehicles, Pedestrians and Animals.
Project Packages This project is proposed to be divided into 6 packages.
Mode of Implementation The Project will be implemented on Engineering, Procurement and Construction (EPC) Mode.
S. No. Subject Uploading Date View/Download
  Status of Resumption of Construction work of Bundelkhand Expressway from 20.04.2020 Size:210KB | Lang:English 21-04-2020 Click here to View/Download
  KMZ File for Bundelkhand Expressway
Size: 1.1MB | Lang: English
14/02/19 Click here to View/Download
 

The contract with the builders of the projects was executed by the state government for the construction of Bundelkhand Expressway and Gorakhpur Link Expressway projects.Size:392.85KB| Lang: Hindi

30/12/2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:60.67KB | Lang: Hindi 24-12-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:60.68KB | Lang: Hindi 16-12-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:60.67KB | Lang: Hindi 09-12-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:60.65KB | Lang: Hindi 02-12-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:60.67KB | Lang: Hindi 26-11-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:57.20KB | Lang: Hindi 18-11-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:57.17KB | Lang: Hindi 04-11-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:57.15KB | Lang: Hindi 30-10-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:57.17KB | Lang: Hindi 22-10-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:57.17KB | Lang: Hindi 14-10-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:57.18KB | Lang: Hindi 9-10-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:54.30KB | Lang: Hindi 30-09-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:54.36 KB | Lang: Hindi 26-09-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:54.3 KB | Lang: Hindi 25-09-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:54.32 KB | Lang: Hindi 24-09-2019 Click here to View/Download
  Land Acquisition Details Of Bundelkhand Expressway Size:54.2 KB | Lang: Hindi 23-09-2019  Click here to View/Download

 
 